| Parameter | Detail |
| Partner | Canon Tien Son Factory |
| Core products | Thermal Energy Storage (TES) |
| Cold Storage Capacity | 8,000 kWh |
| Payback Period (ROI) | 4 years |
| Installation location | Outdoor |
| Delivery time | February 2019 |
1 Energy Efficiency Challenges and Requirements
Canon Tien Son Factory, a key production facility of the group, requires a highly reliable cooling system to maintain the rigorous electronics manufacturing process. Operating a large Chiller system during peak production hours significantly increases operating costs.
Project objectives:
-
Provides additional, stable cooling capacity to the production environment.
-
Implement strategies to effectively cut electricity costs during peak hours.
-
Install sustainable solutions in outdoor areas, in accordance with industry standards.
2 Large Capacity Outdoor Cold Storage Tank Solution
ESS Vietnam has deployed an outdoor reinforced concrete Cold Storage Tank (TES) solution with a capacity of 8,000 kWh , designed to withstand industrial and weather conditions:
-
Optimizing Electricity Costs: The system takes advantage of low electricity price periods to store 8,000 kWh of cooling capacity . This capacity is used to reduce the load or replace the operation of the main Chiller during peak hours.
-
Production Assurance: Cold storage helps maintain stable production temperatures, eliminating the risk of interruption due to lack of cooling capacity during peak hours.
-
Industrial Durability: The above ground concrete tank construction ensures long design life and easy integration into the plant Utilities system.
3 Investment Efficiency and Implementation Results
The Canon Tien Son project is a typical example showing that TES is a strategic investment, bringing sustainable financial benefits and improving operational efficiency.
-
Reliable Financial Performance: The ability to save on electricity costs during peak hours helps the project achieve a payback period (ROI) of 4 years , in line with long-term industrial investment expectations.
-
Delivery Time: The project was completed, installed and put into operation in February 2019 , ensuring continuity in the factory's operations.
3.1 Sustainable System Installation Process
Installation is carried out to a high standard, with a focus on durability and operational accessibility:
-
Concrete ice storage tank at Canon Tien Son factory seen from outside: Image of TES tank with completed structure, ready for operation, demonstrating the solidity and high durability of outdoor concrete structure.

-
Heat exchanger installed inside the tank: Deploy the installation of heat exchangers, the most important component to perform the charging and cooling function of the tank.
-
Tank Operation Access Door: Install dedicated access doors to ensure engineers can easily access the tank for routine inspection and maintenance, maintaining optimal operating performance.
ESS Vietnam is proud to be a strategic partner in the field of energy optimization for leading manufacturing corporations. Contact us to analyze the potential for large-scale energy savings for your industrial project.