| Parameter | Detail |
| Partner | MOVËNPICK Resort Cam Ranh |
| Core products | Thermal Energy Storage (TES) |
| Cold Storage Capacity | 14,700 kWh |
| Payback Period (ROI) | 3 years |
| Installation location | Basement technical area |
| Complete installation | September 2018 |
1 Star Service Challenges and Requirements
As an international 5-star resort, MOVËNPICK Resort Cam Ranh places absolute demands on the stability of the air conditioning system to ensure high quality service. The high demand for cooling, operating continuously 24/7 means very high power consumption, especially during peak hours.
Project objectives:
-
Deploy large capacity energy solutions to ensure cold sources are always available.
-
Cut your electricity costs during peak hours effectively and sustainably.
-
Integrate the system discreetly and securely in the technical area.
2 Large Capacity TES Solution In Basement
ESS Vietnam has supplied and installed a large capacity Cold Storage Tank (TES) solution of 14,700 kWh in the basement of the Resort's technical area . This solution helps the resort:
-
Maximize Electricity Costs: The Chiller system is operated at night (off-peak hours) to produce and store 14,700 kWh of cooling capacity .
-
Ensuring Continuous Cold Supply: This huge amount of reserve cold is released to supply the air conditioning system during the day (peak hours), helping the main Chiller system reduce load or stop operating, thereby reducing peak hour electricity costs.
-
Perfect Integration: The basement location of the technical area is the ideal place to place the pool, helping to optimize the connection with the existing mechanical and electrical system without affecting the architecture and resort space of the hotel.
3 Investment Efficiency and Results Achieved
The MOVËNPICK Resort Cam Ranh project affirms that the TES solution is a smart and necessary investment choice for high-end service projects, where service quality and financial efficiency are top priorities.
-
Fast Payback: With outstanding energy cost savings, the project achieves an impressive payback period (ROI) of just 3 years .
-
5-Star Stability: The TES system ensures an absolutely stable cold source, contributing to maintaining the Resort's 5-star service quality.
-
Completion Time: The project was completed and installed in September 2018 , ensuring the resort's timely operation.
3.1 Installation Process Details
The construction process of the Cold Storage Tank in the basement was carried out with great care and precision:
-
Waterproof membrane inside the tank: Applying a specialized waterproof membrane inside the concrete tank is a key step to ensure insulation and prevent leaks.
-
Heat exchangers in the tank: Install heat exchangers, the most important component to perform the charging and discharging process effectively.
-
Main manifold and heat exchanger in tank: Complete the connection of heat exchangers to the main manifold, preparing for connection to the Chiller system.
-
Tank Access Doors: Install dedicated tank access doors, ensuring accessibility for maintenance and routine inspection.